The final part of the construction of a 12-kilometer highway leading to the «Platov» airborne in Rostov is nearing completion. Specialists SU-872 of the Donaerodorstroy enterprise work at a high rate and excellent work quality.
About 40 road workers are doing shift work on laying the top layer of the highway at the object "Access to the Platov Airport."
According to the head of the project Denis Vorobyov, “Much has been done at the facility, and we are not slowing down. In a round-the-clock mode, our specialists lay the top 5-centimeter layer of the road surface from a fine-grained mixture of asphalt concrete. In some areas, the installation of a metal barrier has already begun.”
According to the information of the chief engineer Viktor Zarzhetsky, the exemplary level of all work at this facility is ensured through the use of modern technologies and materials, “but the most important thing is the professionalism of our road workers, who work day and night, in any weather,”.
In the process of erecting the route leading to the new modern Don airport, a number of units of high-performance equipment are involved: 10 rollers, 2 asphalt pavers, one of which is a 9-meter wide, milling machine, about two dozen units of dump trucks.
With the end of all these works, the level of comfort and road safety will increase, while the speed of the traffic flow will increase.
According to experts, the average daily traffic along the access road to the Platov Airport in the coming years will exceed 10 thousand cars per day.
Technical characteristics of the facility:
The category of road is IB.
The length of the site is 12.4 km.
The number of lanes is 4.
Estimated speed - 120km / h.
The width of the subgrade is 28.5 m.
The width of the carriageway is 2x7.5.
Artificial constructions:
Reinforced concrete bridge over the Rubezhnaya beam: length - 180.80 pm
Reinforced concrete bridge over the Tuzlov River: length - 127.30 pm
Reinforced concrete bridge over the Bolshaya Nesvetai River: length - 106.75 m
Reinforced concrete overpass through a / d at PK22 + 50: length - 27.18 running meters
Reinforced concrete overpass of transport interchange on PK57 + 50: length - 27.18 running meters