The Donaerodorstroy company has launched a contract for the reconstruction of the M-4 Don road section at km 1024 - km 1036 in the Rostov Region as part of the implementation of the Aksai bypass infrastructure project.
Now, the reconstruction of communications for the continuation of the main construction work is nearing completion. In the near future, the road workers will begin to broaden the roadbed (expand the route) towards Moscow, build a bridge over the Tuzlov River and an 83-meter overpass over the road of the municipal street network of the village of Grushevskaya.
The reconstructed 12-kilometer section of the route will be brought up to category IA parameters with 6 lanes and a permitted speed of 110 km / h.
It is important that construction work will be carried out parallel to the existing lanes, and will not affect traffic. This is especially true in the summer, because on the M-4 Don in this section during the peak season, more than one hundred thousand cars pass daily.
The completion date is September 30, 2021.
In total, it was possible to shift 1,463 meters of the gas pipeline, 945 meters of power lines, 178 meters of water supply, and 938 meters of communication lines were laid at the Aksai Bypass facility.
Completely complete all work on the removal of communications bypassing Aksay is planned by the end of 2019.
According to the CEO of Donaerodorstroy Sergey Zubanov, through Aksai there is a path to Moscow, Krasnodar, Sochi, during summer holidays and public holidays, many kilometers of traffic jams occur on this section of the route. The new transport project will improve the transport situation on the territory of the Rostov agglomeration.